Date: September 25, 2024
Project: Covelli Centre Flat Roof Replacement
Contractor: Boak & Sons
Overview: Boak & Sons has commenced the replacement of the flat roof section at the Covelli Centre in downtown Youngstown. This project is a crucial part of maintaining the integrity and safety of the facility.
Current Status:
- Demolition: The old roofing material has been successfully removed.
- Installation: The new roofing materials are being installed. This phase is progressing on schedule, with approximately 50% of the new roof already in place.
- Weather Considerations: The team is closely monitoring weather conditions to ensure that the installation process is not adversely affected.
Next Steps:
- Completion of Installation: The remaining sections of the new roof will be installed over the next two weeks.
- Inspection: A thorough inspection will be conducted to ensure the new roof meets all safety and quality standards.
- Final Touches: Any necessary finishing touches and clean-up will be completed.
Expected Completion Date: Beginning of October
Notes:
- Please be aware of ongoing construction activities around the Covelli Centre and follow any posted safety guidelines.
- We appreciate your patience and cooperation during this essential maintenance work.